Having trouble viewing this email? View online

11 April 2024

Restoration work gathers pace on Tweed's rural road network

Contractor tackles multiple sites on Urliup Road

Urliup Road landslip repair

Inspecting the foundation level on one of the slip sites on Urliup Road. BELOW: Working in challenging conditions on Urliup Road, where narrow roads and steep, forested inclines need to be negotiated.

Urliup Road steep incline

Flood restoration work on the Tweed’s road network continues with Council engaging contractor Hazell Brothers Group to restore six damaged sites caused by landslips from the 2022 floods along Urliup Road.

The $5 million restoration project involves extensive ground restabilisation and road reconstruction works to restore the road to its pre-flood condition.

The project will be undertaken in three stages over a period of approximately 42 weeks, with works currently scheduled for completion by October 2024, weather permitting.

The contractor has commenced work on five of the six sites along Urliup Road, with site establishment, vegetation clearing and temporary access construction completed.

Work crews have also completed preliminary excavation works on the first site and are preparing to commence reconstruction with gabion baskets and soil nails.

Stabilisation works on the upslope slip are more than halfway completed with specialist rope access technicians installing rock anchors for stabilisation using a specialised machine called a Marini.

Council is also in the process of acquiring some private land adjacent to Urliup Road to help with the restoration process, while an easement has been created on a downhill slip site for future maintenance.

Acting Director Engineering Danny Rose thanked the community for their patience while these vital flood restoration works are undertaken.

“This is a challenging project for our flood restoration team, with six landslides and steep and narrow terrain to navigate but we are pleased to see some great progress on restoring Urliup Road to its pre-flood condition,” Mr Rose said.

“It has taken some time to get to the point we are at now with design and approvals and preparatory work recently completed – and we still have at least six months of construction work ahead of us before completion.

“We thank the community for their patience while we undertake these works.”

Mr Rose said while there would be some disruption, particularly for local residents over coming months, Council and its contractor would communicate and provide updates wherever possible.

With works commencing, the road will be temporarily closed to traffic between 9 am and 3 pm, Monday to Friday, between 1041 to 1110 Urliup Road during Stage 1, weather permitting.

Outside of these times, sites will remain open under a single lane will traffic lights to ensure the safety of motorists and on-site crews, and to help facilitate the movement of heavy machinery and equipment.

Motorists are urged to use Hogans and/or Dulguigan roads as alternative routes during work hours. Electronic signage at the start of Urliup Road (both ends) will advise of changed conditions plus any up-to-date information.

To ensure the safety of Council’s waste recovery contractor, temporary arrangements for a communal collection point for waste recovery services will remain in place until after the roadworks are complete, when the service will return to normal.

Find out more about flood restoration works at tweed.nsw.gov.au/flood-restoration-works.

Urliup Road rope access technicians

Rope access technicians drilling soil nails into a bank on Urliup Road.

Downloads

Photo 1: Urliup Road landslip repair
Caption: Inspecting the foundation level on one of the slip sites on Urliup Road.

Photo 2:  Urliup Road steep incline
Caption: Working in challenging conditions on Urliup Road, where narrow roads and steep, forested inclines need to be negotiated.

Photo 3: Urliup Road rope access technicians
Caption: Rope access technicians drilling soil nails into a bank on Urliup Road.

Connection to Council’s Community Strategic Plan:

Stay up to date with Council’s latest news and updates, follow us on social media or subscribe to get all the news direct to your inbox.

Call 02 6670 2136 or email for all media or interview requests.

Visit Council's website    Email Tweed Shire Council Communications    Call +61 2 6670 2136    Follow on Facebook    Follow on Instagram    Follow on Twitter    Follow on YouTube    Follow on Linkedin
Tweed Shire Council wishes to acknowledge the Ngandowal and Minyungbal speaking people of the Bundjalung Country, in particular the Goodjinburra, Tul-gi-gin and Moorung – Moobah clans, as being the traditional owners and custodians of the land and waters within the Tweed Shire boundaries. Council also acknowledges and respects the Tweed Aboriginal community’s right to speak for its Country and to care for its traditional Country in accordance with its lore, customs and traditions.
Tagged as: