Skip to Display Options Skip to Main Content
Level 2 Water Restrictions in place for the Tweed from Friday 13 December. Level 4 restrictions already in place for Tyalgum. Save water now
Aboriginal Acknowledgement A -  |  A +

Email Link   Complying Development Stage 6 - Determination and Issue

You will be sent formal determination and a Complying Development Certificate in accordance with the provisions of the Environmental Planning and Assessment Act 1979 (as amended) together with stamped approved plans and specifications.

A Notice of Commencement form will be enclosed and is to be submitted to Council at least two (2) days prior to commencement of any building work.

A separate letter will be enclosed identifying required inspections including critical stage inspection. NOTE: if critical stage inspections are not undertaken the law prevents the issue of an occupation certificate.

The Complying Development Certificate is valid for 5 years from the date of determination unless building work is substantially commenced beforehand.

Last Updated: