|
The
Kingscliff Wastewater Treatment Plant (WWTP) was designed to treat
sewage collected from the Kingscliff Sewerage Catchment.
The
Kingscliff Wastewater Catchment includes:
-
Kingscliff
-
Fingal
-
Chinderah
-
Cudgen
-
South Kingscliff (Salt)
-
Casuarina
The
treatment plant was commissioned in February 2008. The plant
replaced an out dated and under sized treatment facility. The
facility is located in Cudgen to service a population of 25,000
people. The design flow rate through the plant is 6.0 ML/D.
The
effluent quality discharged achieves very low nutrient limits making
it a world class treatment facility. An educational facility, the
Sustainable Living Centre, has been incorporated into the plant
control building to provide both static and interactive displays to
explain the treatment process.
The
overall project costs for the new facility was $45,000,000.

Aerial Photo of
Kingscliff WWTP February 2008
Treatment Process
The
treatment process for the Kingscliff WWTP is required to meet
stringent effluent discharge requirements that were determined
during the
Environmental
Impact Study for the plant.
A
further requirement was that the process needed to be simple to
operate and extremely robust to guard against shock loads on the
plant.
The
selected process for Kingscliff WWTP is a chemically enhanced
biological nutrient removal (CEBNR) process incorporating the
following stages:
-
Primary Treatment
-
Fine Screening
-
Grit Removal
-
Odour Control
-
Secondary Treatment
-
Anaerobic Reactor
-
Oxidation Tank
-
Secondary Anoxic Zone
-
Secondary Aerobic Zone
-
Clarification
-
Tertiary Treatment
-
Secondary Effluent Pump Station
-
Filtration
-
Chlorination
-
De-chlorination
-
Sludge Management
-
Sludge Lagoons
-
Sludge Dewatering
-
Beneficial Reuse
- Effluent Reuse
The
effluent standards adopted for Kingscliff WWTP are consistent with
best practice treatment technologies.
EPA Licence limits for Kingscliff WWTP (12684)
February 2008
|
Parameter |
Units |
50th
Percentile Concentration |
90th
Percentile Concentration |
|
Requirements for environmental discharge (to Tweed River)
|
|
Biological Oxygen Demand |
mg/L |
10 |
20 |
|
Total
Suspended Solids |
mg/L |
15 |
30 |
|
Total
Nitrogen |
mg/L as N |
5 |
10 |
|
Ammonia |
mg/L as N |
2 |
4 |
|
Total
Phosphorous |
mg/L as P |
0.5 |
1.0 |
|
Oil &
Grease |
mg/L |
5 |
10 |
|
Faecal
coliforms |
cfu/ 100
mL |
100 |
600 |
|
pH |
- |
Range 6.5
to 8.5 |
Primary Treatment
Raw
sewage flows are pumped to the inlet channel via twin 500 mm
pipelines that receive pumped flows from the Kingscliff Sewerage
Catchment. Inlet flows are monitored via flowmeters installed on
each pipeline.
Fine Screening
The raw
sewage passes through a step screen to allow debris to be removed
from the flow. Automatic screening is provided by a 3mm step screen
where screenings are “stepped” up the screen and discharged through
a chute into the screenings screw conveyor. The screenings are
washed, compressed and discharged directly from the screw wash press
to the storage bin.
Raw
sewage can bypass the step screen if blocked or off-line and flow
via an overflow weir with a manual screen.
Grit Removal
The grit
removal system comprises a vortex grit chamber and a classifier.
Grit is settled in the vortex chamber by centrifugal flow within
the tank.
Settled
grit, collected in the base of the grit tank, is periodically
removed via a grit pump to a classifier where the grit is washed and
dewatered prior to discharge to a storage bin
Odour Control
Odour
control is used to minimise odours from the inlet works. The inlet
works are completely covered to contain odourous gases produced
within the sewerage system. An extraction fan to removes the odour
from within the inlet works to the odour control unit.
The
odour control unit treats the odour in a two stage process involving
a biological trickling system followed by an activated carbon
system. This system is designed to remove 99.9% of all odours
within the system.
Secondary Treatment
The Kingscliff WWTP secondary process is based on the 5-stage
Phoredox Process (“Modified Bardenpho”), in the form of an oxidation
tank design. Magnesium Hydroxide (MHL) and Alum are also dosed to
ensure that the specified effluent quality is achieved

Kingscliff WWTP
Secondary Process Diagram
Anaerobic Reactor
Sewage
enters the first chamber of the compartmentalised anaerobic reactor
(total of four chambers), where it is mixed with return activated
sludge, magnesium hydroxide (MHL), and alum. Four submersible
mixers (one per anaerobic chamber) ensure that the raw sewage,
return activated sludge (RAS) and chemicals are completely mixed.
The anaerobic reactor is designed to reduce biological phosphorus.
Oxidation Tank
Aeration
in the oxidation tank is provided by three (2 No. duty/1 No.
standby) surface aerators fitted with variable speed drives.
Dissolved oxygen (DO) concentrations in the oxidation tank are
monitored by two DO probes. Controlling the amount of air provided
to the system (by changing the aerator speeds), results in optimised
nitrogen removal capabilities.
Waste
activated sludge and scum is withdrawn from the oxidation tank,
adjacent to the secondary aerobic reactor. Kingscliff WWTP has been
designed to operate at an average sludge age of 25 days.
Secondary Anoxic and Aerobic Zone
Mixed
liquor transfers from the oxidation tank, to the secondary anoxic
reactor. A submersible mixer located in the anoxic reactor ensures
that the contents are fully mixed, and solids settling is
prevented. Mixed liquor flows to the secondary aerobic chamber,
where two submersible aerators ensure that residual ammonia-nitrogen
is converted to nitrate-nitrogen in order to meet the stringent
ammonia-nitrogen licence conditions.
Clarification
Mixed
liquor is distributed evenly between two circular clarifiers via a
centre feed well. The clarifiers contain a scraper that
concentrates the return activated sludge (RAS) in the centre of the
clarifier’s base where it is extracted and returned to the anaerobic
reactor. Effluent overflows the clarifier launders to the filter
feed (secondary effluent) pump station.

Return
Activated sludge pump station
Tertiary Filtration
The
filter feed pumps transfer the secondary effluent from the
clarifiers to the micro-screening filtration system. The flow is
evenly split between two filter units. Effluent passes through the
20 micron filter medium, and particulates are trapped on the surface
of the medium. Periodically a backwash cycle is initiated, which
cleans the filter medium. Backwash water is returned back to the
plant inlet works where it is retreated.
Chlorination
Filtered
effluent flows under gravity to the chlorine contact tank (CCT).
Sodium hypochlorite is dosed at the inlet to the CCT distribution
chamber. Chlorinated effluent flows through the CCT, which provides
contact time to ensure disinfection is achieved.
Service
water is used on-site for washing down equipment and flushing
lines.
Dechlorination
Final
effluent (being filtered and disinfected) flows from the
Chlorination Contact Tank to the dechlorination chamber. Sodium
bisulphite is dosed into the chamber to dechlorinate the effluent
prior to release to the discharge point.
Once
fully treated, effluent is reused or is pumped to the Tweed River
outfall.
Sludge Management
Waste
activated sludge is pumped from the oxidation tank to the anaerobic
sludge lagoons. Biosolids are further stabilised using 4 anaerobic
sludge lagoons. Each lagoon has a volume of approximately 3,900m3.
Stabilisation also reduces odour in the dewatered sludge.

Sludge
lagoons
Supernatant (clear water on top) from the lagoon is recycled via a
site utility pump station to inlet works.
Sludge
from the lagoons is pumped into averaging tanks then pumped to the
centrifuge and dewatered. The dewatering process is based on
centrifugal force. To help the sludge coagulate, polymer is fed into
the process. After the water has been separated from the sludge the
water is drained off from one end.
The
dewatered sludge is fed to the sludge bin loading conveyer which
feeds the sludge cake storage hopper. Centrate is continuously
decanted and flows via gravity to the site drainage pump station.
Sludge
cake storage hopper holds 50m3 of dewatered sludge that
can be reused on cane fields or broad acre farms as a soil
conditioner.
The
Tweed Valley has sufficient area of cane fields available to allow
the sludge to be beneficially reused in a sustainable manner. To
ensure that no nuisance odours occur, the biosolids are incorporated
into the top soil within 2 hours of application.
Effluent Reuse
The
chlorinated effluent is sent to Chinderah Golf Course for beneficial
reuse as well as being used onsite .

Aerial Photo of Kingscliff WWTP and
surrounding area 2008 |